In 2019, Facility Services identified that the boilers at Fossil Ridge High School were failing and would require replacement during the summer of 2020. The District subsequently hired PEC, an engineering consultant the District uses to provide mechanical engineering services, to develop drawings for the replacement project.
Through Invitation for Bid (IFB) #20-345-001, PSD solicited qualified contractors to submit bids for all material and labor associated with the replacement of the boilers at Fossil Ridge High School as designed by PEC.
As a result of the IFB, bids were received from 2 qualified contractors. After review of the bids, Facility Services and Procurement determined Colorado Mechanical Systems was the lowest responsive bidder as indicated on the Bid Tabulation Sheet, a copy of which is attached for the Board’s review.
The limited scope contract between the District and Colorado Mechanical Systems in the amount of $405,830.00 is attached for the Board’s review.